Flowline
Wolf Lake Loop Project
Client
Inter Pipeline
Project
Flowline
Timeline
September 2010 to December 2010
Location
Bonnyville, Alberta
Project Highlights
Fabrication and Installation of piping, pumps, meter skids allowing for capacity flow increases at the LaCorey & Wolf Lake Facility Sites. Up to and including 24" OD pipe.
Support sub contractors for the installation of Electrical, Instrumentation and Piles.
Cutting, capping and installation of structural steel support members and landings.
Assist with Nitrogen purging and de-energizing of existing production lines.
Perform multiple 24 hr shut downs in order to connect new scope with existing.