Pipeline Construction
Pembina Vantage Pipeline Project
Client
Pembina
Project
Pipeline Construction
Timeline
March - Nov 2013
Location
Maple Creek to Assiniboia SK
Project Highlights
The Vantage Pipeline consisted of the construction and installation of 328 km of 10”Gr. 359 Cat II, Carbon Steel Pipe. In addition to the pipeline construction the project entailed the installation of 2 pigging facilities and 12 Block Valve settings.
M&N controlled and assisted in the installation of over 100 crossings, completed by Horizontal Directional Drilling with bore sections ranging in length from 50 to 500 meters.
The Vantage Pipeline was the longest Cross Country Pipeline Project that M&N Construction has completed to date and represents a significant project accomplishment to our company and employees. The project crossed various terrains from the Cypress Hills to flat and sandy prairie landscapes, through treaty land and various environmentally sensitive areas requiring delicate construction
methods.
The project required a peak crew size above 300 employees and subcontractor’s which became the largest single spread, managed by M&N Construction.
M&N Energy Services Motto
“Our work is never so urgent or important that we cannot take time to do it safely.”
M&N Energy Services Ltd.
Box 249
4511 Victoria Avenue
Coronation, AB
T0C 1C0
403-578-2016 |
[email protected] |
- © M&N Energy Services Ltd.
- |
- Privacy Policy
- |
- Website Credits